Projects in Maharashtra State included under CADWM
Sl.
No.
Name of Project
Date of inclusion
Completion target date under CADWM
Completion target date under AIBP
CCA
(Ha.)
ICA
(Ha.)
Estimated cost
(Rs. Lakh)
CA released
(upto March 2019)
(Rs. Lakh)
1
Arjuna
18.08.2017
31.03.2019(O)/ 31.12.2019 (R)
Dec-19
5704
5704
2894.01
80.798
2
Aruna
08.12.2017
31.03.2020 (O)
Dec-19
5310
5310
2025.86
0
3
Bawanthadi
29.07.2016
31.03.2018 (O)
Completed
2500
-
1563.03
52.62
4
Bembla
18.08.2017
31.03.2020 (O)
Dec-19
45708
40170
25985.36
950
5
Dhom Balkwadi
19.04.2010
31.03.2015(O)/ 31.12.2020(R)
June-19
28100
18100
6525.6
843.51
6
Gadnadi
18.08.2017
31.03.2020 (O)
Dec-19
3111
-
1912.93
3.991
7
Gosikhurd
15.02.2018
31.03.2020(O)/ 31.03.2021(R)
Dec-21
176107
176107
74372.51
938
8
Khadakpurna
18.08.2017
31.03.2020 (O)
June-19
15720
-
7942.14
265.8
9
KKLIS
18.08.2017
31.03.2020(O)
Dec-19
52824
52824
13268.78
381.5
10
Kudali
17.10.2017
31.03.2020(O)
Dec-19
5327
5327
2675.82
0
11
Lower Dudhna
29.07.2016
31.03.2018 (O)
Dec-19
30040
28698
14549.01
810.096
12
Lower Pedhi
17.10.2017
31.03.2020 (O)
Dec-20
10192
10192
4388.17
0
13
Lower Wardha
25.07.2016
31.03.2019 (O)/ 31.03.2020 (R)
Jun-20
62450
53221
20086.06
2063.4
14
Morna (Gureghar)
18.08.2017
31.03.2020 (O)
Dec-19
4229
3806
1679.57
28
15
Sangola Br. Canal
18.08.2017
31.03.2020 (O)
Dec-19
6883
6883
3244.87
192.732
16
Tarali
29.06.2017
31.03.2020 (O)
Dec-19
13086
14276
5363.53
131.246
17
Tillari
29.07.2016
31.03.2018 (O)/ 31.03.2019(R)
Jun-19
6680
6680
3242.78
481.388
18
Upper Kundalika
18.08.2017
31.03.2020(O)
Jun-19
2700
2700
1425.01
52.241
19
Upper Penganga
27.10.2017
(31.03.2020)(O)
Jun-20
104000
104000
6962.00
300.123
Note: (O) - Original, (R) - Revised