List of ongoing projects under PMKSY-AIBP
(Amount in Rs. Crore)
Sl. No.
Name of the Project
Type of Project (Major/Medium)
CA released as on 3/2019
Target date of completion/ Date of completion report
A
VIDC
1
Bawanthadi Interstate Project
Major
27.49
Completed/NR
2
Bembla
Major
121.57
Dec-19
3
Dongargaon
Medium
5.89
Completed/ 24.04.2019
4
Gosikhurd (NP)
Major
362.43
Dec-21
5
Khadakpurna
Major
40.22
Dec-19
6
Lower Pedhi
Major
10.49
Dec-20
7
Lower Wardha
Major
141.42
Jun-20
B
GMIDC
1
Lower Dudhna
Major
49.40
Dec-19
2
Upper Kundlika
Medium
9.62
Dec-19
3
Upper Penganga
Major
93.48
Jun-20
C
KIDC
1
Arjuna
Medium
9.10
Dec-19
2
Aruna
Medium
0.00
Dec-19
3
Gadnadi
Medium
1.55
Dec-19
4
Nardave
Medium
12.08
Dec-19
5
Tillari Interstate Project
Major
11.94
Dec-19
D
MKVDC
1
Dhom Balakwadi
Major
27.19
Dec-19
2
Krishna-Koyna LIS
Major
83.12
Dec-19
3
Kudali
Medium
1.12
Dec-19
4
Morna
Medium
0.33
Dec-19
5
Sangola Br. Canal
Major
8.87
Dec-19
6
Tarali
Major
30.82
Dec-19
7
Warna
Major
Completed/NR
8
Wang
Medium
0.32
Dec-19